How Long Commercial Construction Really Takes in Northeast Wisconsin
Design, approvals, procurement and construction all shape the completion date. Here is how to plan the full sequence. Discuss Your ProjectAll ArticlesPlanning and budgeting
The honest answer
Most owners ask how long construction takes. The better question is how long the whole thing takes, because construction is usually the shorter half. Design, plan review and permitting routinely consume as much calendar as the building itself.
Start with delivery method, because it decides the rest
The CII/Pankow Revisiting Project Delivery Performance, 1998–2018 report gives these median delivery speeds for its newer 212-project sample:
- Design-build: 4,704 square feet per month
- Construction manager at risk: 3,655 square feet per month
- Design-bid-build: 1,721 square feet per month
The 6,842 and 3,250 figures belong to the original 1998 benchmarks. These sample medians should not be divided into your floor area to promise a completion date. Build the schedule around your scope, site, approvals and procurement instead.
Plan review is the part nobody budgets for
Confirm the review path before setting a start date. The DSPS commercial building program explains when plan review is required and when an authorized municipality can review a project. DSPS reviews are submitted through eSLA; local permits must also be coordinated with the municipality.
Allow time for a complete submission and corrections
Review queues change. Use the current DSPS plan review information and metrics, or obtain current timing from the delegated reviewer. Include time for supporting documents, payment, reviewer questions and any required resubmission.
Confirm fees and conditions for your project
The design team should confirm the required submissions, review fees and conditions for starting construction. Budget them alongside local permits rather than relying on a generic online estimate.
A realistic sequence for a mid-size project
- Programming and budget. What you need, what the site allows, what it will cost. Weeks, not months, if the contractor prices as they draw
- Design. Runs in parallel with pricing in design-build. This is where most of the time gets won or lost
- Plan review and local permits. Confirm current queues, submission requirements and correction time with the responsible authorities
- Sitework and foundations. Weather dependent in Wisconsin, which is the real argument for starting design in autumn
- Steel. Long lead. In design-build it can be released as soon as the frame is settled instead of waiting for a full bid set
- Enclosure, then interior. Enclosure reduces weather exposure, but temporary heat, material temperature requirements and winter logistics still need to be planned
- Commissioning and occupancy. Inspections, punch list, final occupancy
The Wisconsin seasonal reality
Foundations in February are possible and expensive. The single most valuable scheduling decision in this climate is getting the building enclosed before deep winter, which means working backward from a target enclosure date rather than forward from a start date. A contractor who self-performs concrete and steel can hold that date far more reliably than one coordinating three subcontractors with their own backlogs.
Schuh runs its own concrete, steel fabrication, steel erection and carpentry crews, plus our own crane fleet and operators. That is the whole reason our schedules hold.
Get a real date
Tell us the site and the square footage and we will walk you through the actual sequence, including which review path your site falls under. Discuss your project or call (920) 833-6465.
Talk to Schuh
Call (920) 833-6465 or send a project inquiry and we will come back with next steps.
Planning a building, addition or renovation?
Tell us about the project and we will come back with next steps. Or call (920) 833-6465.